Stage 3 · Execute & Build
Schedule the work, track progress on site and manage RFIs, submittals and punch lists.

Construction Pro

SLA dashboard · photo-markup punchlist · weather-impacted day tracker.

AI Insights & Next Best Actions

Grounded in the latest snapshot of this module

Click Generate to produce an executive summary and a prioritised action list from current data.

RFIs Overdue
2
Avg RFI Age
9d
Submittals Overdue
1
Avg Submittal Age
13d
RFIs
IDTitleAge / SLAOwnerStatus
RFI-401ICU door clearance — Floor 411d / 7dArchitectOpen
RFI-402Medical gas outlet spacing OT-15d / 5dMEP Eng.Responded
RFI-403Slab penetration — pharmacy chase1d / 7dStructuralOpen
RFI-404Ceiling height conflict — lobby24d / 10dArchitectOpen
RFI-405Finish schedule — Reception4d / 5dInteriorsClosed
Submittals
IDTitleAge / SLAOwnerStatus
SUB-201Anesthesia workstation product data14d / 14dClinicalPending Review
SUB-202Antimicrobial flooring sample12d / 10dArchitectRevise & Resubmit
SUB-203Surgical light shop drawings8d / 14dMEP Eng.Pending Review
SUB-204MRI shielding calculations26d / 21dRadiology PEPending Review
SUB-205Lobby lighting cut sheets3d / 7dArchitectApproved